Planned maintenance: Eugene, Salem, Corvallis Optical Upgrades, multiple nights, 2018-07-31 to 2018-08-09 00:00-06:00

Stephen Fromm stephenf at nero.net
Thu Aug 2 02:02:53 PDT 2018


The second night of maintenance in Eugene is complete.

Please contact the NERO NOC if you have questions or concerns:

email: noc at nero.net
phone: 541.346.6376


On Thu, 2018-07-26 at 12:26:50 -0700, Richard Hicks wrote:
> NERO will begin upgrades to our Optical infrastructure on July 31st. The plan involves no impact software upgrades the first night, then upgrades to the optical
> hardware as scheduled below.
>
> Most NERO customers will not be impacted as work will be staged to allow redundant circuits to transition traffic to alternate paths.
>
> Customers with impacted optical circuits will be contacted directly.
>
> Dates:
> 2018-07-31 00:00-06:00 - Software updates
> 2018-08-01 00:00-06:00 - Eugene NERO POP
> 2018-08-02 00:00-06:00 - Eugene NERO POP - If needed
> 2018-08-03 00:00-06:00 - Salem Amplification Site
> 2018-08-04 00:00-06:00 - Salem Amplification Site - If needed
> 2018-08-06 00:00-06:00 - Salem NERO POP
> 2018-08-07 00:00-06:00 - Salem NERO POP - If needed
> 2018-08-08 00:00-06:00 - Corvallis NERO POP
> 2018-08-09 00:00-06:00 - Corvallis NERO POP - If needed
>
> Please contact the NERO NOC if you have questions or concerns:
>
> email: noc at nero.net
> phone: 541.346.6376


-- 