Planned Maintenance: Eugene Hub MetroE circuits, 2014-10-05, 0000-0500

Richard Hicks rhicks at nero.net
Fri Oct 3 08:52:39 PDT 2014


NERO has been notified by LS Networks of planned maintenance on Sunday,
October 5th between 0000-5000 for MetroEtherent circuits coming into the
NERO Eugene Hub site. Intermittent outages are expected throughout the 
maintenance window.

This will affect the Eugene leg of the Eugene/Medford/Klamath Falls
backbone circuit and the following MetroE connected customers:

OSU Extension Service Coos County
OSU Extension Service Linn County
OSU Extension Service Curry County
OSU Extension Service Lincoln County
OSU Extension Service Douglas County

If you have any questions and/or concerns, please contact the NERO NOC at:

email: noc at nero.net
voice: 541.346.6376

Thanks,
Rick

-- 
Richard Hicks                       Email:      rhicks at nero.net
NERO Network Engineer               Phone:         541.346.1713
UO Computing Center                   FAX:         541.346.4397
1225 Kincaid                     NERO NOC:         541.346.6376
Eugene, OR 97401               GPG Key ID:             F651340D

Fingerprint: 3388 28B9 3E02 F462 03E9  14C6 B57B CBDF F651 340D



More information about the outages mailing list